The following example shows a message for a successfully completed hot copy:

nuodb [domain] > show process status host localhost pid 16689

NodeID: 1  NodeState: RUNNING  Clients: 0 
Hot Copy: started at 2015-04-09 14:10:35 
          ended at 2015-04-09 14:10:35 
          copying to /hotcopyResults/test_archive 
          status completed

If you happen to display the process status while the SSM is shutting down then you might see a status cancelled message. This appears only very briefly.

Another way to determine whether a hot copy operation successfully completed is to look for the archive destination directory that was specified when hotcopy was invoked. If the directory exists then the hot copy operation successfully completed.